Since 1962, we constantly expanded, innovated, adjusted our methods and offers becoming over the years a key player of automotive recycling in France.
From the garden where everything started, to the 24 hectares of today and an ultra-modern warehouse tomorrow, we aim once more to revolutionize our field and invest in an exceptional industrial process.
THE PROJECT
The project consists in creating as early as September 2019 a 12 000 m² warehouse on ground and 17 000 m² on total surface. It will host three activities: disassembling vehicles, storing our parts and shipping them.
This building and the 24-hectares extension will be completed in June 2020.
A section of the storage yards will be covered with photovoltaic carports (learn more).
This project allows GPA to stay the French leader in terms of ground surface and vehicle-recycling capacity.
GPA TODAY
> A 3000m² warehouse and 16 outdoor storage tents
> 12 hectares of storage yards
> 30 vehicles disassembled per day
> 400 shipments per day
> 80000 used parts in stock
GPA TOMORROW (November 2019)
> A 17000m² production, storage and shipment facility
> 24 hectares of storage yards
> 70 vehicles disassembled per day and per team
> 1000 shipments per day
> 156000 used parts in stock
THE CONSTRUCTION SITE
The construction work is divided between 3 phases extending from September 2018 to June 2020 :

Phase 1 :
Beginning of construction and grading of the extension yards (September 2018)

Phase 2 :
Erection of the new 7000m² building and commissioning of the disassembly line (delivery in November 2019)

Phase 3 :
Addition of 5000m² to the already existing 7000m² warehouse (delivery in June 2020)